Estimating Tips

The following helpful tips will help when placing a concrete order.

  • Use the concrete calculator.
  • Figure depths and widths as they have been built on the site, not simply what the plans say
  • Never try to order the exact amount of concrete that is needed.
  • Include a margin of safety when calculating out your concrete yardage. There are more problems caused by underestimating the amount of concrete than having extra concrete. A perfectly placed order of concrete will finish the job with a small amount left over. An order that comes up a small amount short is costly.-

Extra costs of coming up short when ordering concrete can include:

  • Overtime for the crew
  • A short load charge from the ready mix supplier
  • Possible extra charge from your concrete pumping service
  • A cold joint can occur (where one pour ended and another pour began)

For general rule of thumb for margin of safety consider ordering as follows:

If your order isOrder this much extra
1-5 cubic yards.25-.5 c.y. extra
6-10 c.y..5 -1 c.y. extra
11-20 c.y..5-1.5 c.y. extra